Madison Beltline (US 12/14/18/151) Improvements

Contacts

Madison Beltline (US 12/14/18/151) Improvements

The 20-mile section of the Madison Beltline from just north of the US 12 and US 14 (University Avenue) interchange to the US 12/18 and County N interchange in Dane County is being studied to determine how to best meet the transportation needs of the corridor.

A variety of improvements have been recommended to accommodate the growing traffic volumes and improve safety within the corridor. The following were constructed in 2008 or will be by 2012:

2008 construction

  • Old Sauk Road

    • Added an additional left turn lane on the northbound ramp.
    • Added an advance left turn lane for westbound traffic between High Point Road and the ramp termini.
    • The southbound exit ramp has one left turn lane and two right turn lanes.
    • Auxiliary lane extensions both north and south between the west ramp terminals and Excelsior Drive.
    • The northbound exit ramp has two left turn lanes and one right turn lane.
  • Mineral Point Road

    • Added a triple left turn lane to the northbound exit ramp.
    • Extended the northbound exit ramp right turn lane.
    • Added a westbound auxiliary lane between the Target entrance and the Beltline.
    • Added southbound exit ramp dual right turn lanes.
  • Seminole Highway

    • Signal and lane reconfiguration work at both ramp terminals and approaches. Bike and Pedestrian lanes are provided on the west side of the bridge.
  • Park Street

    • Constructed additional left turn lane on the westbound off ramp to provide one right turn lane and two left turn lanes.
  • Rimrock Road

    • Constructed an additional right turn lane on the westbound off ramp to provide for dual right turn lanes and one left turn lane.
  • Segment between Old Sauk Road and Gammon Road

    • Resurfaced the east and westbound lanes up to the ramp terminals at each end.
  • US 51/Stoughton Road

    • Constructed an additional left turn lane on the eastbound off ramp.

2009 construction

  • Fish Hatchery

    • Remove the eastbound off ramp.
    • Add an additional southbound and 200 foot left turn lane southbound on Fish Hatchery.
    • Lengthen deceleration lane for eastbound traffic entering the northbound exit loop ramp.

2010 construction

  • Park Street

    • Remove the existing eastbound on ramp and reconstruct with the new alignment.
    • Signalize the northbound movement at the eastbound off ramp and Park Street.
    • Remove the northbound off ramp.
    • Relocate the frontage road to make room for southbound and new northbound exit ramps.
    • Realign southbound/northbound exit ramp.
    • Create dual left turn lanes and connection from southbound to northbound terminal.
    • Lengthen the acceleration lane from the eastbound on ramp through the bike and pedestrian bridge.
    • Lengthen the deceleration lane on Park Street to the westbound on ramp.
  • Segment between Rimrock Road and Park Street

    • Extend auxiliary lanes.

2012 construction

  • Fish Hatchery

    • Remove remaining loop ramp from northbound Fish Hatchery to westbound Beltline traffic.
    • Align ramps on the north side of the interchange.
    • Widen bridges to accommodate dual left turn lanes.

Other study recommendations will be implemented beyond 2012 based on congestion, safety and funding availability.

Top Return to top


Madison Beltline.

 

Related information:

Madison Beltline (US 12/14/18/151) Safety and Operations Study

 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index