Burlington bypass project - schedule

East project | West project

Late 2003 through 2007: Real estate activities occured.

March 2004 through spring 2007: Final design work completed on east project.

Spring 2006 to fall 2007: Construction of the first contract of the east project began in the spring of 2006. This work consists of grading a majority of the 5.7 miles of the Burlington bypass east project. The bypass remains closed until completion of the third contract in the fall of 2008. Reconstruction of three side roads occurs as part of the first contract on the east project:

  • WIS 142 - About 0.7 miles of WIS 142 and 400 feet of Mount Tom Road is reconstructed from spring to fall of 2006. WIS 142 was reopened to traffic in the fall of 2006. Ramps connecting WIS 142 to the bypass are graded and remain closed.
  • WIS 11 - About one mile of WIS 11 was reconstructed from spring to fall of 2007. WIS 11 is reopened to traffic in the fall of 2007.
  • County A - About 0.6 miles of County A, 200 feet of Old County A and 200 feet of River Road was reconstructed from spring to fall of 2006. County A is reopened to traffic in the fall of 2006. Ramps connecting County A to the bypass are graded and remain closed.

Top Return to top

Fall 2006 to fall 2007: Construction of the WIS 36/83/bypass interchange as well as the Fox River bridges (north) and Fox River bridges (south) began in the fall of 2006 as part of the second contract on the east project. WIS 36/83 remains open to traffic through the construction, but is reduced to one lane in each direction. Construction of the bridges and WIS 36/83/bypass interchange were completed in the fall of 2007; however, access to the bypass will remain closed until completion of the east project in fall 2008.

Fall 2007 to fall 2008: The third and final contract of the east project will begin in the fall of 2007 with the placement of embankments for the Brever and Ketterhagen Road overpasses. The majority of work for the third contract will take place in 2008. The work will consist of paving and completion of the mainline bypass as well as the construction of the following side roads:

  • WIS 83 - About 0.5 miles of WIS 83 will be reconstructed from spring to fall of 2008. WIS 83 will remain closed until project completion in fall of 2008.
  • WIS 142 ramps – The WIS 142 ramps will be paved and completed by fall of 2008. Access to the bypass will open upon completion of the east project.
  • Yahnke Road – WIS 83 / Yahnke Road intersection will be removed. Access to Yahnke Road will be restored via the bypass at the completion of the west project in the fall of 2010.
  • Brever Road - About 0.4 miles of Brever Road will be reconstructed from fall 2007 through summer of 2008.
  • Ketterhagen Road - About 0.4 miles of Ketterhagen Road will be reconstructed from fall 2007 through summer of 2008.
  • County A ramps – The County A ramps will be paved and completed by fall of 2008. Access to the bypass will open upon completion of the east project.

Top Return to top

Fall 2008: Burlington Bypass east project completed and open to traffic from WIS 83 to WIS 36/83.

Summer 2006 through spring 2009: Final design work completed on west project.

January 2008 to summer 2009: Construction of the first contract of the west project will begin in January of 2008. Work will consist of grading 2.9 miles of the total 5.2 miles of mainline bypass on the west project. The mainline bypass will be graded from .4 miles west of Spring Valley Road to WIS 83. Bridges will be constructed over Spring Brook and the JW Peters Quarry Conveyor. The bypass remains closed until completion of the third contract in the fall of 2010. Side road work in the first of three contracts for the west project is as follows:

  • WIS 36 southeast ramp – Grading for the WIS 36 southeast ramp will begin in the spring of 2008 to provide access for construction. The ramp connecting WIS 36 to the bypass will remain closed until completion of the west project.
  • Spring Valley Road - About 0.4 miles of Spring Valley Road will be reconstructed. Spring Valley Road will be open to traffic by fall of 2008.
  • JW Peters Conveyor Access Road – The JW Peters Conveyor and access road will be reconstructed with a lower profile to provide for two overpass structures to carry bypass traffic over the conveyor. The reconstruction of the conveyor and access road will begin in January of 2008 and be completed by summer of 2008. Work on the overpass structures will continue until fall.
  • County P southwest ramp – Grading for the County P southwest ramp will begin in the spring of 2008 to provide access for construction. The ramp connecting County P to the bypass will remain closed until completion of the west project.
  • Yahnke Road - About 0.2 miles of the Yahnke Road Spur will be constructed on new alignment, connecting existing Yahnke Road to the bypass. This work will begin in the spring of 2008 and will be completed in the fall of 2008. Access to the bypass via Yahnke Road Spur will remain closed until completion of the west project.

Top Return to top

Spring 2009 to summer 2010: Construction of the second contract of the west project will begin in the spring of 2009. This work will consist of grading an additional .8 miles of the total 5.2 miles of mainline bypass on the west project. The mainline bypass will be graded from just south of existing WIS 11 to just north of WIS 36. Bridges will be constructed over the White River. The bypass remains closed until completion of the third contract in the fall of 2010. Side road work in the second of three contracts for the west project is as follows:

  • WIS 11 - Grading for the WIS 11 on new alignment will begin in the spring of 2009 to provide access for construction. WIS 11 to stay open to traffic. The WIS 11 connection to the bypass will remain closed.
  • WIS 36 - About 0.9 miles of WIS 36 will be reconstructed. Traffic will be detoured via WIS 11 and WIS 120 during construction. WIS 36 will open to traffic by late fall of 2009. Access to the bypass will remain closed until completion of the west project.
  • County P - About 0.8 miles of County P will be reconstructed. In addition, 500 feet of Brookview Avenue will be constructed. Traffic will be detoured via WIS 50, WIS 83 and Market Street during construction. County P will open to traffic by late fall of 2009. Access to the bypass will remain closed until completion of the west project.

Top Return to top

Spring 2010 to fall 2010: Construction of the third contract of the west project will begin in the spring of 2010. This work will consist of grading the remaining 1.5 miles of the total 5.2 miles of mainline bypass on the west project as well as paving its entire length and connecting ramps. Side road work in the third of three contracts for the west project is as follows:

  • WIS 11 - Existing WIS 11 will transition to and become the Burlington bypass. Old WIS 11 will intersect the bypass near County DD. Traffic will be detoured via WIS 36 and WIS 120 during construction. Old WIS 11 will be open to traffic along with the entire bypass at the completion of the west project in the fall of 2010.
  • County DD - About 0.8 miles of County DD will be constructed on new alignment. County DD will intersect with Old WIS 11 approximately 0.5 miles east of its existing intersection with WIS 11. Existing County DD will become a cul-de-sac near its existing intersection with WIS 11. There is not planned detour of County DD. County DD will be open to traffic in the fall of 2010.
  • WIS 36 southeast ramp – WIS 36 southeast ramp will be paved and completed by fall of 2010. Access to the bypass will be open upon completion of the west project.
  • County P ramps – County P ramps will be paved and completed by fall of 2010. Access to the bypass will be open upon completion of the west project.
  • Yahnke Road - Access to the bypass will be provided via the Yahnke Road Spur. Existing Yahnke Road will become a cul-de-sac south of the bypass. Existing Yahnke Road north of the bypass to WIS 83 will be removed. Access to the bypass will be open upon completion of the west project.

Fall 2010: Burlington Bypass west project completed and open to traffic from WIS 11 to WIS 83.

Top Return to top


 

 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index