skip navigation Wisconsin Department of Transportation
Wisconsin Department of Transportation Logo
Plans and Projects
 
Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

WIS 83 project

Need

Schedule

Maps

Environmental documents

Public involvement

Contacts

WIS 83 project

WIS 83 is an important north-south highway serving regional traffic between I-43 at Mukwonago and WIS 16 at Hartland, as well as local traffic generated by development along the highway.

The 17-mile section of WIS 83 between Waukesha County NN and WIS 16 has been studied to determine how to best meet the long-term transportation needs of the corridor.  

The WIS 83 corridor study determined five projects were necessary to accommodate the growing traffic volumes and improve safety along the corridor:

  • I-94 to WIS 16, resurface the existing lanes from Golf Road to north of Cardinal Lane
  • High Meadow Lane to I-94, resurface the existing lanes
  • The WIS 16 and WIS 83 interchange from Capital Drive to Campus Drive, reconstruct and expand four lanes
  • County NN to WIS 59
    • Reconstruct County NN to County X, four lanes
    • Construct two lanes on ultimate four lane from County X to Walnut/Seville
    • Two lane curb and gutter from Walnut/Seville to Old Village Road
    • Widen shoulders and improve signals from Old Village Road to WIS 59
  • County DE to High Meadow Lane, reconstruct and expand four lanes

The first project, I-94 to WIS 16, is expected to being in the spring of 2008.


Vehicles traveling on WIS 83.

 

 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index