Date Stage Type of work/activity
October 11, 2007   Public information meeting (PIM) was conducted.
May 21, 2008   PIM was conducted.
March 25, 2009   PIM was conducted.
April – July 2009 1 Milwaukee County - Reconstruct westbound lanes while 2-way traffic is placed on the existing eastbound lanes. The Kildeer Court segment closest to Brown Deer Road also will be reconstructed in halves with it remaining open to 2-way traffic during this time. 
August – October 2009 2 Milwaukee County - Reconstruct eastbound lanes while 2-way traffic is placed on the new westbound lanes.
November 2009 3 Milwaukee County - Complete median area with some intermittent lane closures.


 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index