WIS 45-100 Corridor Study - schedule

Date Type of work/activity
April 2007 Began study (information gathering).
July 2007 Existing operations analysis.
October 2007 Development of preliminary alternatives.
Nov. 14, 2007 1st public informational meeting (PIM) was conducted.
Winter 2008 Refine alternatives based on public input.
April 17, 2008 2nd PIM was conducted
June 2008 Value engineering study.
Nov. 12, 2008 3rd PIM was conducted.
Fall 2009 Selection of preferred alternative.
Sept. 30, 2009 PIM #4 scheduled.
Spring 2010 Public hearing to be conducted (if requested).
Summer 2010 Finalize preliminary roadway plans.


 

 

 


Drivers & Vehicles | Safety | Travel | Plans & Projects | State Patrol | Doing Business | Programs for Local Gov't

Air | Bicycles | Bus/transit | Cars | Motorcycles | Pedestrian | Rail | Trucks | Waterways

Home | News | About Us | Research & Library | A-Z Index